"Oracle has sent a force majeure notice to the developer of Project Jupiter, a S...

@AkaSci@fosstodon.org

"Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, as reported by Bloomberg.

Force majeure clauses excuse a party from contractual obligations when events outside its control get in the way. The notice would allow Oracle to delay payments should the facility miss its 2028 target.

The project, opposed by residents and env groups, has become a political flashpoint ahead of the midterm elections."

techcrunch.com/2026/09/24/orac
1/n