UK's Hinkley Point C new nuclear plant delayed to 2030 as costs climb to €56 bil...

@Sustainable2050@mastodon.energy

UK's Hinkley Point C new nuclear plant delayed to 2030 as costs climb to €56 billion*, i.e. €17,500 per kW.
EDF said the first reactor at the site in Somerset will begin operations in 2030, a year later than in the last update – almost 13 years after construction work began – after a series of delays to the project.
theguardian.com/uk-news/2026/f
*) £35 bn in 2015 prices = £49 bn now = €56 bn