Got the breakers, PDU wall brackets, and new GPU for the CI VM server. PDU is co...
Andrew Zonenberg @azonenberg@ioc.exchange
Got the breakers, PDU wall brackets, and new GPU for the CI VM server. PDU is coming tomorrow, then I think I'm ready for Tuesday's maintenance window.
Also picked up a NEMA 5-20 extension cable so I can run the main IT rack off a non-UPS wall outlet in another room while working in the lab panel.
This means that while the T&M equipment and endpoint workstations will be down during the entire maintenance window, the critical core stuff (router, switching, VM server, storage cluster) will have only two reboots worth of downtime as I switch them from UPS to normal power, then back after the maintenance window is over. (Assuming that grid power doesn't go out while I'm doing maintenance on the UPS panel... Unlikely but you never know)