Data centre in Co. Mayo has planning permission overturned on grounds it breaches national climate policy.

An Coimisiún Pleanála ruled that the applicants had failed to show there was sufficient electricity locally to serve the centre and they had no on-site renewable energy to compensate. They also said there was also a lack of evidence that the project had any corporate purchase power agreement with a renewable energy supplier.