Oracle invoked a 'force majeure' notice to protect itself from financial liabili...

@cdarwin@c.im

Oracle invoked a 'force majeure' notice
to protect itself from financial liability
and defer rent payments regarding Project Jupiter,
a massive 2.45-gigawatt AI data center campus in Doña Ana County, New Mexico, built to support OpenAI

The 1,400-acre site has faced local opposition and infrastructure hurdles,
including a denied permit for a planned natural-gas pipeline,
prompting a shift toward costly fuel cells from Bloom Energy.

The legal provision allows Oracle to protect itself
and potentially delay financial/rent payments
if power-related setbacks or permitting delays prevent the campus from opening by 2028.

reuters.com/