“You have to really love somebody to drive them to LAX,” said Eli Lipmen, execut...

@cdarwin@c.im

“You have to really love somebody to drive them to LAX,” said Eli Lipmen, executive director of Move LA, a local non-profit coalition that organizes for improved transit and housing.

Enter the people mover:
a long-awaited rail line of less than 2.5 miles (4km) that would offer congestion relief by finally providing a direct rail connection between terminals, a ride-share zone, a new transit center and a car rental hub.

The project, officially named SkyLink, broke ground in 2019 under then mayor Eric Garcetti.
Since then, the city has been through a lot. A global pandemic. A pair of devastating fires. The Dodgers winning the World Series thrice. Trump 2.0’s immigration raids and the massive protests in response. Two mayors and a new one on the way.

And in those nearly eight years, the LAX people mover’s elevated track has gone up and its train cars are rolling between stations
-- but they’re moving precisely zero people.

It’s also gone more than $1bn over budget, and is expected to overshoot its intended 2023 opening date by four years (and counting).

The project
– part of a $30bn plan to modernize LAX
– has been hampered by disputes between the contractor hired to execute it and the city, along with a litany of technical issues.

Officials report the project is 99% complete,
but the final testing phase, which requires at least 30 consecutive days of uninterrupted operation,
has stretched more than 200 days.

An estimated opening has been pushed back multiple times,
and is now slated for 2027.

More public scrutiny came after a video circulated on local media showing an electrical explosion on the track,
for which city officials have not explained a cause.

In September, the credit agency Fitch Ratings downgraded the project’s debt to a B-, just shy of deeming it a substantial credit risk.

L.A.'s newly elected mayor Raman,
who holds a master’s degree in urban planning from MIT,
has called for a full investigation into the project
and said she would refer any alleged evidence of criminal wrongdoing
“to the appropriate authorities”.

When she’s sworn in as mayor next month,
LAX’s train troubles will become her responsibility.

And the goalposts keep shifting.
Last week, Linxs moved the people mover’s projected opening back again,
now to March 2027.
theguardian.com/us-news/2026/n