In case you were curious what the current [gestures broadly] environment has done to enterprise computing prices, this rack, stack, and configuration is for a 7-node VxRail cluster with NetShelter rack and 8 total network switches.

In April 2024 as part of project estimation, a vendor quote was provided to us for total cost of $342k USD. This includes the above components, jumper cables, power cables, APUs, and software licensing for the VxRail and vSphere/ESXI deployment (and all the subset things to be provided on the VMs). More or less the total package.

In July of 2025 as we were looking to begin purchasing, a new quote was provided for the same components of $881k USD.

Due to issues with project scheduling, approvals, staff turnover, and other unforeseen occurrences, purchasing never occurred while the previous quote was active. We re-quoted in December 2025. Same components, total cost of $1.2m USD.

We've now been asked to bid for a sister plant, and the same rack. I was part of the meeting yesterday to nail down expected engineering hours, but got a look at the rest of the proposal. We received a preliminary quote a couple weeks ago for $1.7m USD.

When asked to estimate, roughly, what prices are expected to be 9 months, which would be near to project start should we win the bid, the vendor gave an offhand expectation of in the neighborhood of $2.4m USD


RE: https://zoner.work/notes/aqdue2yikhxm03le