NON COMPLIANT ELECTROMECHANICAL RELAYS Florence, SC, 06/17/2026 On July 17, 2026...
NRC Event Notification Reports @whoopsie@tds.xyz
NON COMPLIANT ELECTROMECHANICAL RELAYS
Florence, SC, 06/17/2026
On July 17, 2026, during calibration of a KF relay, ABB identified a deviation from the specified coil-assembly drying process. The affected coil assembly had completed the required air-drying stage, however, the subsequent force-drying (baking) stage had not been performed. The applicable process specifications required dipped transformers and coil assemblies to undergo a defined air-drying period followed…
https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2026/20260814en.html#en58409